Connected load
connected_load_kw
Connected mechanical load from LOAD-05-MECH-SCHED-01
Scores if within ±3% of the reference value.
Calculates source-bound electrical feeder metrics from a deterministic SSC-05 task-owned source pack. The template combines mechanical equipment demand, future allowance, power-factor correction, three-phase feeder current, cable ampacity derating, breaker continuous loading, voltage drop, and an overall synthetic pass score.
with-tool: The model is given an executable Python calculator script.
Standards
One template produces many comparable benchmark tasks while keeping the scoring contract fixed.
01
The reusable contract shown on this page.
02
An archetype and site context are sampled.
03
Inputs may be hidden at harder tiers.
04
The model responds with the declared outputs.
Inputs the model receives, and the outputs it is scored on.
23 inputs
Included directly in every task prompt.
Pump motor
pump_motor_kw
LOAD-05-MECH-SCHED-01 chilled-water pump motor rating
Pump quantity
pump_quantity
LOAD-05-MECH-SCHED-01 chilled-water pump quantity
Pump demand factor
pump_demand_factor
LOAD-05-MECH-SCHED-01 chilled-water pump demand factor
Ahu motor
ahu_motor_kw
LOAD-05-MECH-SCHED-01 AHU motor rating
Ahu quantity
ahu_quantity
LOAD-05-MECH-SCHED-01 AHU quantity
Ahu demand factor
ahu_demand_factor
LOAD-05-MECH-SCHED-01 AHU demand factor
Dosing pump
dosing_pump_kw
LOAD-05-MECH-SCHED-01 dosing pump motor rating
Dosing quantity
dosing_quantity
LOAD-05-MECH-SCHED-01 dosing pump quantity
Dosing demand factor
dosing_demand_factor
LOAD-05-MECH-SCHED-01 dosing pump demand factor
Future allowance pct
future_allowance_pct
LOAD-05-CALC-01 future allowance applied to demand load
Initial power factor
initial_power_factor
LOAD-05-CALC-01 uncorrected power factor
Target power factor
target_power_factor
LOAD-05-CALC-01 target corrected power factor
Selected capacitor
selected_capacitor_kvar
LOAD-05-CALC-01 selected capacitor bank size
Feeder voltage
feeder_voltage_v
FEEDER-05-MCC-01 nominal three-phase feeder voltage
Feeder length
feeder_length_m
CABLE-05-FDR-01 route length from MSB-05 to MCC-05
Feeder voltage drop mv per a m
feeder_voltage_drop_mv_per_a_m
CABLE-05-FDR-01 source-owned voltage-drop factor
Base cable ampacity
base_cable_ampacity_a
CABLE-05-FDR-01 base cable ampacity before derating
Ambient derating factor
ambient_derating_factor
CABLE-05-FDR-01 ambient temperature derating factor
Grouping derating factor
grouping_derating_factor
CABLE-05-FDR-01 grouping derating factor
Installation derating factor
installation_derating_factor
CABLE-05-FDR-01 installation derating factor
Breaker trip
breaker_trip_a
PROT-05-BKR-01 breaker trip rating
Breaker continuous factor
breaker_continuous_factor
PROT-05-BKR-01 continuous loading factor
Max voltage drop percent
max_voltage_drop_percent
CRIT-05-VDROP-01 owner maximum feeder voltage drop
17 outputs
connected_load_kw
Connected mechanical load from LOAD-05-MECH-SCHED-01
Scores if within ±3% of the reference value.
demand_load_kw
Demand load after source-owned demand factors
Scores if within ±3% of the reference value.
future_allowance_kw
Future allowance applied to the demand load
Scores if within ±3% of the reference value.
design_load_kw
Demand load plus future allowance
Scores if within ±3% of the reference value.
initial_reactive_power_kvar
Reactive power before power-factor correction
Scores if within ±3% of the reference value.
required_capacitor_kvar
Capacitor kVAr required to reach the target power factor
Scores if within ±3% of the reference value.
selected_capacitor_margin_kvar
Selected capacitor size minus required capacitor kVAr
Scores if within ±3% of the reference value.
corrected_apparent_power_kva
Apparent power after correction to the target power factor
Scores if within ±3% of the reference value.
feeder_current_a
FEEDER-05-MCC-01 three-phase current after power-factor correction
Scores if within ±3% of the reference value.
derated_cable_ampacity_a
CABLE-05-FDR-01 ampacity after source-owned derating factors
Scores if within ±3% of the reference value.
ampacity_margin_a
Derated cable ampacity minus feeder current
Scores if within ±3% of the reference value.
breaker_allowable_current_a
PROT-05-BKR-01 continuous allowable current
Scores if within ±3% of the reference value.
breaker_margin_a
Breaker continuous allowable current minus feeder current
Scores if within ±3% of the reference value.
voltage_drop_v
FEEDER-05-MCC-01 source-owned voltage drop
Scores if within ±3% of the reference value.
feeder_voltage_drop_percent
FEEDER-05-MCC-01 voltage drop percentage
Scores if within ±3% of the reference value.
voltage_drop_margin_percent
Owner maximum voltage drop minus calculated feeder voltage drop
Scores if within ±3% of the reference value.
overall_pass_score
1.0 when PFC, ampacity, breaker, and voltage-drop margins are non-negative
Scores if within ±0.1% of the reference value.
Each template is sampled at three tiers. Harder tiers may hide inputs, forcing the model to infer them from the scenario description.
For this template, difficulty scales through parameter and scenario ranges rather than hidden information.
The exact instruction and parameter contract used to generate this task, pinned to the published library source.
/workspace
Teal lines show Jinja input conditions, not task visibility policy. A line renders only when that input or tool is visible.
1You are an electrical design engineer checking a task-owned synthetic SSC-05 mechanical-load feeder, power-factor, ampacity, breaker, and voltage-drop package.2 3Use only the task-owned synthetic source pack values shown below for numeric grading. ETAP, EasyPower, SKM PowerTools, and AS/NZS 3008.1.1-style workflows shape the context only; this instance does not run those tools or parse a real one-line, cable schedule, protection curve, or load-flow export.4 5## Scene6 7- Feeder design case: `CASE-SSC05-FEEDER-001`8- Mechanical load schedule: `LOAD-05-MECH-SCHED-01`9- Load calculation table: `LOAD-05-CALC-01`10- Single-line diagram: `SLD-05-MCC-01`11- Upstream switchboard: `SWBD-05-MSB-01`12- Mechanical control centre: `MCC-05`13- Feeder: `FEEDER-05-MCC-01`14- Cable schedule row: `CABLE-05-FDR-01`15- Protective device row: `PROT-05-BKR-01`16- Voltage-drop criterion: `CRIT-05-VDROP-01`17- Electrical design memo: `MEMO-05-ELEC-LOAD-01`18 19## Mechanical Load And Power-Factor Basis20 21| Item | Value |22|------|-------|23| Chilled-water pump motor rating | {{ pump_motor_kw }} kW |24| Chilled-water pump quantity | {{ pump_quantity }} |25| Chilled-water pump demand factor | {{ pump_demand_factor }} |26| AHU motor rating | {{ ahu_motor_kw }} kW |27| AHU quantity | {{ ahu_quantity }} |28| AHU demand factor | {{ ahu_demand_factor }} |29| Dosing pump motor rating | {{ dosing_pump_kw }} kW |30| Dosing pump quantity | {{ dosing_quantity }} |31| Dosing pump demand factor | {{ dosing_demand_factor }} |32| Future allowance | {{ future_allowance_pct }} % |33| Initial power factor | {{ initial_power_factor }} |34| Target power factor | {{ target_power_factor }} |35| Selected capacitor bank | {{ selected_capacitor_kvar }} kVAr |36 37Load and power-factor checks:38 39- Connected load equals the sum of each equipment rating times its quantity.40- Demand load equals each connected equipment load times its source-owned demand factor, summed across the schedule.41- Future allowance equals `demand_load_kw x future_allowance_pct / 100`.42- Design load equals demand load plus future allowance.43- Initial reactive power equals `design_load_kw x tan(acos(initial_power_factor))`.44- Target reactive power equals `design_load_kw x tan(acos(target_power_factor))`.45- Required capacitor kVAr equals initial reactive power minus target reactive power.46- Selected capacitor margin equals selected capacitor bank minus required capacitor kVAr.47- Corrected apparent power equals `design_load_kw / target_power_factor`.48 49## Feeder, Cable, Breaker, And Voltage-Drop Basis50 51| Item | Value |52|------|-------|53| Feeder voltage | {{ feeder_voltage_v }} V |54| Feeder length | {{ feeder_length_m }} m |55| Voltage-drop factor | {{ feeder_voltage_drop_mv_per_a_m }} mV/A/m |56| Base cable ampacity | {{ base_cable_ampacity_a }} A |57| Ambient derating factor | {{ ambient_derating_factor }} |58| Grouping derating factor | {{ grouping_derating_factor }} |59| Installation derating factor | {{ installation_derating_factor }} |60| Breaker trip rating | {{ breaker_trip_a }} A |61| Breaker continuous factor | {{ breaker_continuous_factor }} |62| Maximum voltage drop | {{ max_voltage_drop_percent }} % |63 64Feeder checks:65 66- Feeder current equals `corrected_apparent_power_kva x 1000 / (sqrt(3) x feeder_voltage_v)`.67- Derated cable ampacity equals `base_cable_ampacity_a x ambient_derating_factor x grouping_derating_factor x installation_derating_factor`.68- Ampacity margin equals derated cable ampacity minus feeder current.69- Breaker allowable current equals `breaker_trip_a x breaker_continuous_factor`.70- Breaker margin equals breaker allowable current minus feeder current.71- Voltage drop in volts equals `feeder_voltage_drop_mv_per_a_m x feeder_current_a x feeder_length_m / 1000`.72- Feeder voltage drop percent equals `voltage_drop_v / feeder_voltage_v x 100`.73- Voltage-drop margin equals maximum voltage drop percent minus feeder voltage drop percent.74- Overall pass score is `1.0` only when selected capacitor margin, ampacity margin, breaker margin, and voltage-drop margin are all non-negative; otherwise it is `0.0`.75 76## Output Format77 78Write a compact memo to `/workspace/output.md`. Include a source-boundary statement that this is a task-owned synthetic source pack. Explain the calculations briefly, preserve the object IDs above, and state whether the baseline source pack passes the current docs-only checks.79 80Do not claim authority approval, accepted project evidence, software export validity, full standards compliance, executable real source-pack parsing, generated ETAP/EasyPower/SKM evidence, generated benchmark readiness, or benchmark readiness.81 82Include a fenced JSON block with exactly these numeric keys:83 84```json85{86 "connected_load_kw": <numeric_value>,87 "demand_load_kw": <numeric_value>,88 "future_allowance_kw": <numeric_value>,89 "design_load_kw": <numeric_value>,90 "initial_reactive_power_kvar": <numeric_value>,91 "required_capacitor_kvar": <numeric_value>,92 "selected_capacitor_margin_kvar": <numeric_value>,93 "corrected_apparent_power_kva": <numeric_value>,94 "feeder_current_a": <numeric_value>,95 "derated_cable_ampacity_a": <numeric_value>,96 "ampacity_margin_a": <numeric_value>,97 "breaker_allowable_current_a": <numeric_value>,98 "breaker_margin_a": <numeric_value>,99 "voltage_drop_v": <numeric_value>,100 "feeder_voltage_drop_percent": <numeric_value>,101 "voltage_drop_margin_percent": <numeric_value>,102 "overall_pass_score": <numeric_value>103}104```105 Each generated task is drawn from one of these realistic scenario bands.
Site contexts ground each scenario in a real locale the model can use to infer hidden values.
ssc05_mechanical_feeder_case
Mechanical load schedule tied to one SLD feeder, cable, breaker, voltage-drop criterion, and electrical memo
mechanical-load-feeder-voltage-ssc05-mechanical-feeder-case-preview — hard difficulty, all inputs given.
Mechanical load schedule tied to one SLD feeder, cable, breaker, voltage-drop criterion, and electrical memo. mechanical-load-feeder-voltage. Required outputs: connected_load_kw, demand_load_kw, future_allowance_kw, design_load_kw, initial_reactive_power_kvar, required_capacitor_kvar
Scenario context and visible inputs.
Executable tool: mechanical-load-feeder-voltage-package_calc.py
Inputs withheld at this difficulty.
Nothing. All inputs are supplied.
The scored JSON answer schema.
{
"connected_load_kw": <number>,
"demand_load_kw": <number>,
"future_allowance_kw": <number>,
"design_load_kw": <number>,
"initial_reactive_power_kvar": <number>,
"required_capacitor_kvar": <number>,
"selected_capacitor_margin_kvar": <number>,
"corrected_apparent_power_kva": <number>,
"feeder_current_a": <number>,
"derated_cable_ampacity_a": <number>,
"ampacity_margin_a": <number>,
"breaker_allowable_current_a": <number>,
"breaker_margin_a": <number>,
"voltage_drop_v": <number>,
"feeder_voltage_drop_percent": <number>,
"voltage_drop_margin_percent": <number>,
"overall_pass_score": <number>
}